Flasher Improvement District

City of Flasher Improvement District Kick Off Schedule
As of August 24, 2015

MilestoneStartCompleted
Process presented  April 15, 2015
Proposal presented  April 15, 2015
On Call Services April 15, 2015 October 15, 2015
  • Lead Engineer 5 hours
  
 Boundaries April 15, 2015 May 13, 2015
  • Lead Engineer 5 hours
  • Design Engineer 7 hours
  • Clerical 24 hours
  • Web Page 24 hours
  
Resolution May 13, 2015 May 13, 2015
Assessment Formulas April 15, 2015  June 15, 2015 
  • Lead Engineer 3.5 hours
  • Design Engineer 1 hour
  • Clerical 5 hours
  • Graduate Engineer 42 hours
  
Testing and Inspections  
  • Televising Sewers
May 18, 2015May 29, 2015
    • Lead Engineer 1 hour
    • Design Engineer 2 hour
    • Grad Engineer 2 hours
    • Cad Tech 12 hours
  
  • Water System Testing
 May 18, 2015 May 29, 2015
    • Lead Engineer 3 hours
    • Grad Engineer 12 hours
  
 Street Inspections (City to Complete) May 1, 2015  June 1, 2015
 Storm Sewers (City to Complete)  May 1, 2015  June 1, 2015
 Preliminary Results  July 8, 2015
  • Lead Engineer 4 hours
  • Cad Tech 4 hours
  • Grad Engineer 6 hours
  
 Data Collection and Modeling  
  • Survey Control
 September 
  • System Models
    • Water system
    • Sanitary sewer system
    • Storm sewer system
 September 
  • Testing and Inspections Support
  October
 Standards Report July 1, 2015 September 1, 2015
 Recommendations  October
  • Report
  • Schedule
  • Costs
  
 Special Assessment Commission  October
 Financial Assistance October Ongoing
  • Pending Applications
  • Approved Grants
  • Approved Loans
  • Proposed Assessment Reduction
  
 Public Meetings  October
  • Scheduled
  • Post-meeting Reports
  
 Interim Meetings Ongoing 
 Implement Plan  November