Ulteig has acquired Affinity Energy to expand our resources and expertise. Learn More

  • BUCHANAN, STUTSMAN COUNTY, ND
  • Power

Buchanan Substation and Tap Line

Ulteigā€™s support of a new distribution substation site and 43.8 kV transmission tap line in Buchanan, Stutsman County, North Dakota, involved performing a title search, the development of a landowner database and the creation of a landowner aerial map for the route.

Ulteig negotiated easements with landowners along the 3.5-mile route. The team also completed a land value analysis within the project corridor and drafted easement documents and legal descriptions. Finally, the team successfully negotiated and secured signatures from all landowners, acting as liaison during construction and providing project deliverables to the Central Power Electric Cooperative organization.

Where We Work

We have locations throughout North America

 

View All Locations

Careers

Become an Employee-Owner now!

View Careers